DNO G99 Grid Connection Fast Track Guide for Solar in Great Britain
Updated 6 September 2026 · By SolarNevs Research Desk, Dealer surveys + verified sources · 3 sources · Method ↗

Key Takeaways
- Where an energy installation is classified as apply to connect, installers must submit an Engineering Recommendation G99 application before installing the device.
- The standard assessment window requires the DNO to respond within 45 days for low voltage energy devices and within 65 days for high voltage systems.
- Installers can utilise a fast track application process by submitting the G99 Form A1-2 for fully type-tested integrated microgeneration and storage.
- Fast track processing reduces DNO connection review to 10 days or less.
- Under statutory ESQCR Regulation 22, parallel operation requires agreeing specific requirements with the distributor and fitting equipment to prevent danger or interference.
- It is the legal responsibility of the energy device owner to ensure the DNO has granted formal authorisation before work commences.
Understanding Apply to Connect vs Fast Track Pathways
In Great Britain, connecting embedded generation to the public electricity distribution network is administered by regional Distribution Network Operators (DNOs). When an installation exceeds the microgeneration threshold of 16 amperes per phase, it is designated as apply to connect.
Connection Pathway | Applicable Systems / Criteria | DNO Review Timeline | Statutory / Form Reference |
|---|---|---|---|
G99 Fast Track | Fully type-tested integrated solar PV and battery storage | 10 days or less | ENA Form A1-2 / Type Test Register |
Standard Low Voltage (LV) | Energy devices exceeding 16A per phase (LV network) | Up to 45 days | Engineering Recommendation G99 (or G100) |
High Voltage (HV) | Commercial / industrial high-voltage grid connections | Up to 65 days | Engineering Recommendation G99 / DNO formal offer |
Parallel Grid Operation | Grid-tied generation operating concurrently with network | Prior approval required | ESQCR 2002 Regulation 22 |
Switched Alternative | Changeover / backup power isolated from mains network | Must prevent parallel running | ESQCR 2002 Regulation 21 |
According to national guidance issued by the Department for Energy Security and Net Zero:
- If an energy device is classified as apply to connect, installers must submit the relevant Engineering Recommendation G99 application form (or G100 if export is limited) to the DNO before installing the device to ensure safe and effective operation of the electricity network.
- Under standard procedures, the DNO will be in touch within 45 days for low voltage energy devices and 65 days for high voltage energy devices to approve the installation or request modifications.
The G99 Fast Track Procedure: Form A1-2
To prevent administrative backlogs for standard residential and small commercial hybrid systems, the Energy Networks Association established the fast track mechanism.
Eligibility Criteria
If battery storage is being implemented with a generation device and falls under apply to connect, installers can utilise a fast track application process. This involves submitting the G99 Form A1-2 application form for connection of Fully Type Tested Integrated Microgeneration and Storage installations.
10-Day Accelerated Decision Window
The application must be submitted prior to physical installation, but it dramatically accelerates network sign-off:
- Submitting Form A1-2 reduces the connection time to 10 days or less.
- Both the solar inverter and the battery storage inverter must be registered as fully type-tested on the Energy Networks Association Type Test Register.
- If the energy device is not type tested, the DNO may require additional documentation to demonstrate that it complies with relevant engineering standards.
Statutory Grid Safety: ESQCR Regulation 21 and 22
Connecting any electrical power source in parallel with the public distribution grid is governed by primary statutory legislation under the Electricity Safety, Quality and Continuity Regulations 2002.
Statutory Regulation 22 Duties
Under Regulation 22, no person shall install or operate a source of energy in parallel with a distributor's network unless the installer:
- Has the necessary and appropriate equipment to prevent danger or interference with that network or with the supply to consumers so far as is reasonably practicable.
- Agrees specific requirements with the distributor who owns or operates the network.
- Ensures the source of energy is configured to disconnect itself electrically from the parallel connection when the distributor's equipment disconnects the supply of electricity to the installation.
Switched Alternative Precautions (Regulation 21)
Where a private system is operated as a switched alternative to the mains network (such as off-grid generator changeovers), Regulation 21 requires that the installer shall ensure that the source of energy cannot operate in parallel with the network, and complies with British Standard Requirements.
Owner Responsibilities and Verification
National guidance stresses that legal compliance rests squarely with the property owner:
- Energy device owners must ensure that your installation contractor has notified the DNO of your installation.
- It is the energy device owner's responsibility to ensure that the DNO has received this notification and, in the case when the energy device is classified as apply to connect, granted authorisation before the work is carried out.
Frequently asked questions
What is the DNO G99 fast track process?
The fast track route uses Form A1-2 for fully type-tested integrated solar PV and battery storage, reducing approval times to 10 days or less.
When is an energy installation classified as apply to connect?
Any generation or storage installation exceeding 16 amperes per phase falls under apply to connect, requiring DNO approval before works commence.
How long does a standard G99 DNO connection review take?
DNOs must respond within 45 days for low voltage installations and within 65 days for high voltage connections.
What is the legal basis for parallel grid connection in Great Britain?
Parallel operation is governed by Regulation 22 of the Electricity Safety, Quality and Continuity Regulations (ESQCR) 2002.
Who is legally responsible for ensuring DNO approval is obtained?
It is the energy device owner's responsibility to ensure the DNO grants formal authorisation before installation occurs.
References
- DESNZ Register Energy Devices in Homes or Small Businesses Guidance — accessed 28 August 2026
- Electricity Safety Quality and Continuity Regulations 2002 Regulation 22 — accessed 28 August 2026