Ireland Esb Networks Nc6 And Nc7 Solar Interconnection Guide
Updated 6 September 2026 · By SolarNevs Research Desk, Dealer surveys + verified sources · 3 sources · Method ↗
<!-- hero-pending --> <!-- visual_plan -->
Key Takeaways
- Form NC6 governs micro-generation up to 6 kVA single-phase and 11 kVA three-phase under a zero-cost 'inform and fit' notification procedure.
- Form NC7 covers mini-generation up to 17 kVA single-phase and 50 kVA three-phase, requiring formal technical studies taking 8 to 10 weeks.
- All micro-generation inverters must comply with standard IS EN50549-1 with current Irish settings and be installed to Safe Electric standards.
- For commercial systems above 50 kVA up to 200 kVA, Form NC8 applies with a mandatory external G10 Protection Relay and EGIP witness testing.
- ESB Networks targets smart meter installations within four months of processing a valid NC6 notification.
The Three Interconnection Tiers in Ireland
ESB Networks categorises distributed renewable energy installations into three distinct Low Voltage (LV) connection tiers based on export capacity and inverter rating:
Connection Category | Application Form | System Capacity Boundaries | Application Fee Structure | Grid Operator Processing Workflow |
|---|---|---|---|---|
Micro-Generation | Form NC6 | Up to 25A (6kVA) 1-ph; Up to 16A (11kVA) 3-ph | €0 (Free 'Inform and Fit') | Notification review; smart meter rollout target within 4 months |
Mini-Generation | Form NC7 | 25A (6kVA) to 72A (17kVA) 1-ph; 16A (11kVA) to 72A (50kVA) 3-ph | Application fee invoice with VAT@23% | Formal technical assessment; offer turnaround averages 8 to 10 weeks |
Small Scale Generation | Form NC8 (Inverter) / NC5 (Sync) | >50kVA up to 200kVA 3-ph (inverter); Max 17kVA 1-ph | Application fee is €1245.99 (including VAT@23%) | Detailed engineering study; mandatory G10 relay and EGIP witness testing |
Micro-Generation (Form NC6): The Inform and Fit Process
Under statutory rules, a micro-generator is a source of electrical energy which operates in parallel with ESB Networks LV System and rated up to and including:
- 25 amperes (≈6kVA) at low voltage when the connection is single phase
- 16 amperes (≈11kVA) at low voltage when the connection is three-phase
Key operational parameters for NC6 include:
- Zero Connection Charge: There is no charge to connect a Micro-generator to the ESB network provided it is Micro-generation which can be connected under the 'inform and fit' process i.e. up to 6kVA single phase or 11kVA three phase.
- Quality Compliance: The generator (inverter) must comply with IS EN50549-1 with current Irish settings. Installers must submit an accredited type test certificate.
- Electrical Contractor Accreditation: It is your responsibility to ensure that the Micro-Generator is installed by a registered electrical contractor to Safe Electric standards.
- Smart Metering Deployment: Where customers are eligible to have a smart meter installed during this phase of the rollout, ESB Networks endeavours to install a smart meter within four months of a valid NC6 form being processed by ESB Networks.
Mini-Generation (Form NC7): Commercial Systems up to 50 kVA
When rooftop installations exceed the 11 kVA three-phase microgen threshold, projects transition into mini-generation:
- Capacity Scope: Inverter systems from 25 amperes (6kVA) to 72 amperes (17kVA), when the connection is single-phase, and 16 amperes (11kVA) to 72 amperes (50kVA), when the connection is three-phase.
- Technical Governance: Projects are evaluated under Conditions governing connection operation mini-generation.
- Assessment Timelines: Because larger installations impact local transformer capacity, the average timeframe for the connection offer documents to issue is 8 to 10 weeks from payment of the application fee.
Small-Scale Generation (Form NC8): Systems from 50 kVA to 200 kVA
For large commercial roofs, warehouses, and agribusinesses deploying arrays above 50 kVA:
- Scope: Inverter-connected installed capacity greater than 72amps (≈50kVA) Three Phase and up to 200kVA, or synchronous installed capacity greater than 6kVA and up to 200kVA.
- Mandatory G10 Interface Relay: A G10 Protection Relay is mandatory in all installations under the Small Scale Generation Scheme, providing fail-safe loss-of-mains disconnection.
- Witness Testing: Prior to energisation, developers must contact ESB Networks at egipwitnesstesting@esb.ie, prior to energisation, to arrange EGIP Witness Testing.
Frequently asked questions
What is the difference between ESB Networks Form NC6 and Form NC7?
Form NC6 applies to micro-generation up to 6kVA single-phase or 11kVA three-phase under an inform-and-fit process with no fee, while NC7 covers mini-generation up to 17kVA single-phase or 50kVA three-phase.
What technical standard must solar inverters meet under Form NC6?
Under ESB Networks micro-generation rules, the generator (inverter) must comply with IS EN50549-1 with current Irish settings.
What grid connection process applies to solar installations exceeding 50 kVA?
Systems between 50 kVA and 200 kVA connect under Small Scale Generation via Form NC8, requiring a mandatory G10 protection relay and EGIP witness testing.
How quickly does ESB Networks install a smart meter following NC6 processing?
ESB Networks endeavours to install a smart meter within four months of a valid NC6 form being processed.
References
- ESB Networks Micro-Generation Connection Process — accessed 28 August 2026
- ESB Networks Mini-Generation Connection Guidance — accessed 28 August 2026
- ESB Networks Small Scale Generation Connection Guidance — accessed 28 August 2026
Related guides
More from schemes, subsidies & financing.