Ireland Non Domestic Microgeneration Scheme Ndms Grant Guide

Updated 6 September 2026 · By SolarNevs Research Desk, Dealer surveys + verified sources · 1 source · Method ↗

<!-- hero-pending --> <!-- visual_plan -->

Key Takeaways

  • The Non-Domestic Microgen Grant (NDMG) provides financial assistance to help businesses and other sectors to install solar PV panels to generate electricity on site.
  • Grant funding is available for systems up to a maximum 1000kWp, delivering up to €162,600 in capital support.
  • Grant tiers scale from €1,800 for 2 kWp, €2,100 for 3 kWp, and €2,400 for 4 to 6 kWp, transitioning to €300/kWp (7–20 kWp), €200/kWp (21–200 kWp), and €150/kWp (201–1,000 kWp).
  • SEAI grant offers remain valid for eight months from the date of the formal Letter of Offer.
  • Grid application to ESB Networks takes at least 4 weeks / 20 working days and must be completed before installation commences.
  • Standard grant processing and payment turnaround averages 4 to 6 weeks following document submission.

Purpose and Scope of the NDMG Scheme

Commercial rooftop solar deployment in Ireland is accelerated through the Sustainable Energy Authority of Ireland (SEAI). Specifically, the Non-Domestic Microgen Grant (NDMG) provides financial assistance to help businesses and other sectors to install solar PV panels to generate electricity on site.

The scheme accommodates diverse commercial, public, and non-profit facilities:

  • Eligible Sectors: Businesses, agricultural enterprises, public sector bodies, schools, community centres, and non-profit societies.
  • Capacity Boundaries: Grant funding is available for systems up to a maximum 1000kWp.
  • Maximum Financial Aid: Eligible entities can receive a government grant of up to €162,600.
  • Oversized Systems: A solar PV system with an output of a maximum 1000kWp can be grant funded through the scheme; if the installed capacity exceeds this ceiling, the applicant may claim the maximum grant offering of €162,600.

Tiered Grant Valuation Structure

The grant amount you receive is based on the standard output of your solar PV system. The SEAI publishes a transparent, step-down rate table:

Solar PV System Capacity Band

SEAI Statutory Grant Value

2kWp

€1,800

3kWp

€2,100

4kWp

€2,400

5kWp

€2,400

6kWp

€2,400

7kWp - 20kWp

€300/kWp

21kWp - 200kWp

€200/kWp

201kWp - 1000kWp (1MWp)

€150/kWp

Under this stepped structure, small commercial installations cap at €2,400 for 4 kWp to 6 kWp arrays, before moving to capacity-based incremental additions for larger commercial roofs.

Application Rules, Timelines, and Grid Notice

Securing grant funding requires compliance with statutory administrative milestones:

  1. Prior Letter of Offer: Installers must not start works until an official grant offer is issued. Grant offers are valid for eight months from the date you receive your 'letter of offer'.
  2. ESB Networks Notification: Solar PV companies must coordinate grid permission. They must do this before installing the solar PV system. This application process takes at least 4 weeks / 20 working days.
  3. Disbursement Turnaround: Following installation, all evidence of works must be submitted to the online portal. Please allow between 4 to 6 weeks for payment, with additional time if an inspection is required.

Frequently asked questions

What is the maximum grant available under the SEAI Non-Domestic Microgen Scheme?

Under the NDMG scheme, commercial applicants can receive a government grant of up to €162,600 for installations up to 1,000 kWp.

How are grant values calculated for commercial solar installations?

The grant amount you receive is based on the standard output of your solar PV system, scaling from €1,800 for 2kWp up to €150/kWp for systems between 201kWp and 1000kWp.

How long is an SEAI commercial solar grant offer valid?

Grant offers are valid for eight months from the date you receive your 'letter of offer'.

When must an installer notify ESB Networks before installing solar PV?

Installers must apply to ESB Networks before installing the solar PV system, a process taking at least 4 weeks / 20 working days.